company logo Renovating and Protecting Side Slopes of SHAHID ABBASPOUR Dam Spillway
Physical Progress The project constrauction has been completed.
Satellite image dam spillway  
Agenda(s) Spillway Flip Bucket rectification –sides spillway slope stabilization
Location Khuzestan province

Renovating and protecting area between two buckets of Shaheed Abbas pour dam aimed at reconstructing the damaged flip bucket and stabilization and re-enforcing the sides  spillway of dam to prevent probable falling and erosion when the second power plant structure outlet span of spillway gates are opened